Eight workers can finish a job in 12 days. After 4 days, 4 workers leave. How many days in total does the…

🛠️ Time & Work Hard

Question 12 of 12

Eight workers can finish a job in 12 days. After 4 days, 4 workers leave. How many days in total does the job take?

  1. A 24 days
  2. B 18 days
  3. C 16 days
  4. D 20 days