Question 5 of 12
A is twice as efficient as B. Together they finish a job in 12 days. How many days would A alone take?
- A 18 days
- B 24 days
- C 30 days
- D 36 days
A. 18 days
Step 1: let B do b per day, so A does 2b
→ Step 2: together 3b per day
→ Step 3: total work = 3b × 12 = 36b
→ Step 4: A alone = 36b ÷ 2b = 18 days
→ Answer: 18 days