Question 9 of 12
A, B and C can complete a job alone in 6, 12 and 24 days. All three start together, and after 2 days the work is only done by A and B. When is the job finished (counting from the start)?
- A 3 days
- B 3 1/2 days
- C 3 2/3 days
- D 4 days
C. 3 2/3 days
Step 1: all three together per day = 1/6 + 1/12 + 1/24 = 7/24
→ Step 2: work in 2 days = 14/24 = 7/12
→ Step 3: left = 5/12
→ Step 4: A and B per day = 1/4
→ Step 5: time = (5/12) ÷ (1/4) = 5/3 days
→ Step 6: total = 2 + 5/3 = 11/3 = 3 2/3 days
→ Answer: 3 2/3 days