A can finish a job alone in 10 days. What fraction of the job does A finish in 4 days?
- A 3/5
- B 2/5
- C 2/3
- D 1/4
B. 2/5
Step 1: A's rate = 1 job in 10 days
→ Step 2: work in 4 days = 4 × (1/10)
→ Step 3: = 4/10 = 2/5
→ Answer: 2/5